The No. 2 blast furnace of Tianjin TISCO carbon steel production line started major maintenance work on August 27, involving more than 1600 maintenance items, including the partial replacement of carbon bricks and cooling walls of the furnace cylinder, the replacement of the furnace top airtight box, and the replacement of the hopper under the groove. In order to ensure the smooth completion of maintenance work, leaders at all levels of our company attach great importance to, carefully organized, set up maintenance leading groups, determine maintenance objectives, coordinate to solve problems, issue maintenance instructions, etc., formulate detailed maintenance plans, require each maintenance project to prepare maintenance schedule, to ensure the maintenance of safety, efficient and orderly progress.
Regularly arrange special personnel for maintenance safety monitoring, supervise the implementation of various maintenance measures, coordinate to solve various problems in the maintenance process, grasp the maintenance dynamics in real time, inform the maintenance progress, strengthen the implementation of safety and environmental protection measures for inspection and maintenance projects, eliminate violations, and prevent safety accidents.
With the joint efforts of all staff, on October 09, the No. 2 blast furnace successfully resumed air. After the completion of the overhaul, the utilization coefficient of the blast furnace will be further improved, the fuel ratio will be greatly reduced, and the blast furnace will continue to operate stably on the high-yield platform, helping the company successfully complete the future production objectives.